Project Update – 11/12/17

Work continued removing Mill Pond dam and motivate its impounded sediments downstream.

The removal of Mill Pond Dam was completed to the expected bottom of Sullivan Creek (Photo 1), though a subsurface key of unknown size remains. Work continued removing the log crib dam, with a significant portion having been removed to provide a channel for Sullivan Creek through the dam site. Portions of the log crib dam remain; in the channel, beneath a haul road, and in the opposite bank (Photo 2, 3 & 5). The pond has been completely drained, with water levels dropping more than 35 feet. The delta floodplain was graded by machine, and channels were dug to speed and direct the water to better erode the impounded sediments (Photo 4). With the dam removed water was released from Sullivan lake in significant quantity, flushing sediment from the delta and pond bottom into Sullivan Creek and downstream (Photo 5 & 6).

Public Meeting July 14, 2016

Mill Pond Dam Removal Public Meeting FlyerPlease join Seattle City Light and Pend Oreille PUD staff to learn about the Mill Pond Dam removal and restoration project. This is an opportunity to share your comments about the design of the project and the related project benefits and effects.  

Light refreshments and snacks will be provided.

July 14, 2016
5:30 p.m. – 7:30 p.m.

Cutter Theatre
302 Park Street
Metaline Falls, WA 99153

Questions?
Email: [email protected]
Phone: (206) 386-9854

Design Team Collects Field Data

This past week, the design team was onsite collecting additional field data. They also hosted a public open house to continue sharing project progress with the surrounding community.

IMG_1530
City Light explaining features of the 30% Design – March 23 Public Meeting
IMG_1526
Flagging the expected stream channel path through the delta as the dam is removed
Collecting stream data for new stream channel design
Collecting stream data for new stream channel design

Public Meeting – July 14th

Our next public meeting will be Thursday, July 14th. More details to follow.

Public Open House – March 23, 2016

Please join us for an Open House Wednesday, March 23rd in Metaline Falls. This will take place at the Cutter Theater from 5:30 – 7:30 pm. The project team looks forward to seeing you there.

IMG_1329

  • « Previous Page
  • 1
  • …
  • 5
  • 6
  • 7

Partners


Pend Oreille Public Utility District Logo           Seattle City Light Logo           Forest Service Logo

The Envirocon Design – Build Team


Envirocon Logo           ESA Logo           Natural Systems Design Logo           Mead And Hunt Logo

Copyright © 2025 Mill Pond Dam.