Mill Pond Dam Project

Mill Pond Dam Project

  • About
    • Objectives & Goals
    • Reference Material
  • Updates
  • Progress Gallery
    • Delta Camera
    • Pond Camera
    • General Site Photography
    • Project Videos
  • Schedule
  • Contact

Project Update 8-25-2019

No Envirocon crews on site.  Subcontractors continued picnic shelter construction, Completed handrail construction at the dam/campground, and completed the shotcrete placement on river left at the dam.

1

Project Update 8-18-2019

No Envirocon crews on site.  Subcontractors continued picnic shelter construction, handrail construction at the dam, and prep work for the shotcrete placement on river left at the dam.

Project Update 8-11-19
1

Project Update 8-11-2019

No Envirocon crews on site.  Subcontractors continued picnic shelter construction, jump bridge handrail construction at the dam, and prep work for the shotcrete placement on river left at the dam.

Project Update 8-4-2019

No Envirocon crews on site.  Subcontractors continued picnic shelter construction, jump bridge handrail construction at the dam, and started prep work for the shotcrete placement on river left at the dam.

1

Project Update 7-28-2019

Envirocon crews completed punch list items and demobilization activities.  Subcontractors continued work on the picnic shelter construction and complete the campground paving.

1
  • 1
  • 2
  • 3
  • …
  • 13
  • Next Page »

Partners


Pend Oreille Public Utility District Logo           Seattle City Light Logo           Forest Service Logo

The Envirocon Design – Build Team


Envirocon Logo           ESA Logo           Natural Systems Design Logo           Mead And Hunt Logo

Copyright © 2023 Mill Pond Dam.