Envirocon crews continued the grading of the picnic shelter and assisted the crane subcontractor with the placement of campground and dam pedestrian bridges.
Project Update 6-2-2019
Envirocon crews graded the picnic shelter area and constructed and crane pad at the historic dam location. Crane subcontractor mobilized a 450 ton crane to the campground for the pedestrian bridge placement.
Project Update May 2019
Before: Mill Pond Dam on Sullivan Creek
After: Restored Sullivan Creek after Mill Pond Dam Removal
Project Update 5-10-2019
Small Evirocon crew onsite continuing prep work for 2019 work and assist subcontractors.
Mead & Hunt had one crew member on site to perform quality control on the concrete abutment construction.
Concrete subcontractor onsite continued tying rebar, setting formwork, and poured the footer and backwall.
Project Update 5-3-2019
Small Evirocon crew onsite continuing prep work for 2019 work and assist subcontractors.
Natural Systems Design had two crew members on site assessing the creek alignment, floodplain, and engineered log jams from the previous two seasons work.
Third party survey on site to layout the abutment location for the river right bridge abutment.
Mead & Hunt had one crew member on site to perform quality control on the concrete abutment construction
Concrete subcontractor onsite installing anchors, tying rebar, and placing formwork.
- « Previous Page
- 1
- 2
- 3
- 4
- 5
- …
- 13
- Next Page »