Small Evirocon crew onsite continuing prep work for 2019 work and assist subcontractors.
Natural Systems Design had two crew members on site assessing the creek alignment, floodplain, and engineered log jams from the previous two seasons work.
Third party survey on site to layout the abutment location for the river right bridge abutment.
Mead & Hunt had one crew member on site to perform quality control on the concrete abutment construction
Concrete subcontractor onsite installing anchors, tying rebar, and placing formwork.