Project Update 5-10-2019

Small Evirocon crew onsite continuing prep work for 2019 work and assist subcontractors.

Mead & Hunt had one crew member on site to perform quality control on the concrete abutment construction.

Concrete subcontractor onsite continued tying rebar, setting formwork, and poured the footer and backwall.