At river mile 2.5, a guard rail was installed adjacent to the road and the access ramp to the creek was removed. At river mile 0.3, bulk bags were removed from the Lehigh site and staged on the opposite side of the creek. Helicopter placed ELJs were completed in Sullivan Creek upstream of Mill Pond. The Mill Pond floodplain continued to be graded, and topsoil and woody debris spread throughout the site. Crews continued to plant the floodplain, and upland and riparian areas. Logs were staged at ELJ locations for future installation. Work continued at the southside trail, nearing completion. Concrete debris from the demolished dam were collected and stockpiled for future removal from the site.