Mill Pond Dam Project

Mill Pond Dam Project

  • About
    • Objectives & Goals
  • Updates
  • Progress Gallery
    • Delta Camera
    • Pond Camera
    • General Site Photography
    • Project Videos
  • Schedule
  • Contact

Project Update 10-22-2018

The southside loop and levee trails were completed, and work continued on the terrace trails. All areas of the site to be seeded this construction season were completed. The bank adjacent to the old boat launch was graded back to a stable slope. Access roads to completed areas were decommissioned. ELJ construction continues, working from the top of the site to the bottom, as availability of root wad trees allows. Cable lashings were installed on the helicopter placed ELJs. The construction of the west bridge abutment at the campground continued, with concrete being placed within the void space of the rock pedestal, and the reinforced footing. 

Partners


Pend Oreille Public Utility District Logo           Seattle City Light Logo           Forest Service Logo

The Envirocon Design – Build Team


Envirocon Logo           ESA Logo           Natural Systems Design Logo           Mead And Hunt Logo

Copyright © 2025 Mill Pond Dam.