The west campground bridge abutment was completed. At the east abutment, previously placed boulders were removed, silt was then washed from the boulders and the excavation, the boulders were then replaced. Terrace trails were completed as the roads intersecting them were decommissioned. ELJ construction continues. Trees and sedges salvaged in the spring were planted throughout the site. Portions of the floodplain were graded to design widths. The stockpiled bulkbags at the LeHigh site were hauled to Mill Pond and emptied. Smaller demobilization activities continued throughout the week; picking up miscellaneous trash, debris, tools, unused supplies.