Project Update 11-12-2018

The cap and columns of the east campground bridge abutment were cast, the surrounding areas began to be backfilled and compacted, and the riprap revetment began to be constructed. The remaining crib dam logs were removed from the bank, and the surrounding areas and access was regraded. Access roads throughout the site were rapped.

Partners


Pend Oreille Public Utility District Logo           Seattle City Light Logo           Forest Service Logo

The Envirocon Design – Build Team


Envirocon Logo           ESA Logo           Natural Systems Design Logo           Mead And Hunt Logo