Project Update 11-5-2018

Completing the remaining ELJs. Concrete was placed within the stone foundation of the east abutment, and reinforcement for subsequent placements was prepped in an upland site. Work began removing the remaining crib dam logs from the old dam site, with a significant amount of previously unknown bedrock being exposed beneath the parking lot. Starter channels were excavated and deposited sediments were laid back to stable slopes at the sewer lagoons. Demobilization activities were continued.

 