Trail crews continued the construction of the looping trail to the south. Remaining concrete and log crib timber was removed from the creek at the dam site. The eastern channel at the upper reach continued to be widened to expand the floodplain cross section. Work continued constructing the bank reinforcement structure at the campground. The remaining upland area desiccation cracks were track walked to provide a safe walking surface for future planting activities. Topsoil continued to be spread throughout the middle and lower reaches. A new haul road was constructed adjacent to the campground and the existing access ramp at the campground was abandoned and began to be removed.