Work continued on the east and west ends of the south side trail, the east side was graded and compacted, the west side trail base was graded, and graveled. The river right bridge abutment was excavated and the cut banks laid back. The upper reach at the main channel continued to be graded. All structures at the slide area were completed. Work began at right bank ELJ structures on of the middle reach. Topsoil continued to be placed throughout the site and cut banks graded. Rootwads continue to be delivered to the site. Bollard stones were placed throughout the campground and brush and concrete bollards were removed. Boulders for the helicopter placed ELJs were drilled for anchorages.