Mill Pond Dam Project

Mill Pond Dam Project

  • About
    • Objectives & Goals
  • Updates
  • Progress Gallery
    • Delta Camera
    • Pond Camera
    • General Site Photography
    • Project Videos
  • Schedule
  • Contact

Project Update 9/10/2018

Work continued on the east and west ends of the south side trail, the east side was graded and compacted, the west side trail base was graded, and graveled. The river right bridge abutment was excavated and the cut banks laid back. The upper reach at the main channel continued to be graded. All structures at the slide area were completed. Work began at right bank ELJ structures on of the middle reach. Topsoil continued to be placed throughout the site and cut banks graded. Rootwads continue to be delivered to the site. Bollard stones were placed throughout the campground and brush and concrete bollards were removed. Boulders for the helicopter placed ELJs were drilled for anchorages.

Partners


Pend Oreille Public Utility District Logo           Seattle City Light Logo           Forest Service Logo

The Envirocon Design – Build Team


Envirocon Logo           ESA Logo           Natural Systems Design Logo           Mead And Hunt Logo

Copyright © 2025 Mill Pond Dam.