Crushed rock was placed, graded and compacted at the eastern portion of the south side trail. The main channel at the upper reach continued to be excavated and graded. Logs and armor rock were delivered to the site throughout the week. Boulders for rock collars to be placed by helicopter were weighed and had holes drilled for anchorage. ELJs at river right of the middle reach were constructed. Tops soil continued to be spread at the lower reach.