Mill Pond Dam Project

Mill Pond Dam Project

  • About
    • Objectives & Goals
  • Updates
  • Progress Gallery
    • Delta Camera
    • Pond Camera
    • General Site Photography
    • Project Videos
  • Schedule
  • Contact

Project Update 9-17-2018

Crushed rock was placed, graded and compacted at the eastern portion of the south side trail. The main channel at the upper reach continued to be excavated and graded. Logs and armor rock were delivered to the site throughout the week. Boulders for rock collars to be placed by helicopter were weighed and had holes drilled for anchorage. ELJs at river right of the middle reach were constructed. Tops soil continued to be spread at the lower reach.

Partners


Pend Oreille Public Utility District Logo           Seattle City Light Logo           Forest Service Logo

The Envirocon Design – Build Team


Envirocon Logo           ESA Logo           Natural Systems Design Logo           Mead And Hunt Logo

Copyright © 2025 Mill Pond Dam.