Mill Pond Dam Project

Mill Pond Dam Project

  • About
    • Objectives & Goals
  • Updates
  • Progress Gallery
    • Delta Camera
    • Pond Camera
    • General Site Photography
    • Project Videos
  • Schedule
  • Contact

Project Update 9-26-2018

Work continued constructing ELJs throughout the reach. The bank at the campground was graded and topsoil spread there and throughout the site. Work began on the trails in the upland terraces. Racking bundles, rock collars and root wad trees were prepped for helicopter placements. Grading continued at the upper floodplain, and bridge abutments were excavated. High density planting areas were laid out. Rootwads, logs, and armor stone were delivered throughout the week.

Partners


Pend Oreille Public Utility District Logo           Seattle City Light Logo           Forest Service Logo

The Envirocon Design – Build Team


Envirocon Logo           ESA Logo           Natural Systems Design Logo           Mead And Hunt Logo

Copyright © 2025 Mill Pond Dam.