Work continued constructing ELJs throughout the reach. The bank at the campground was graded and topsoil spread there and throughout the site. Work began on the trails in the upland terraces. Racking bundles, rock collars and root wad trees were prepped for helicopter placements. Grading continued at the upper floodplain, and bridge abutments were excavated. High density planting areas were laid out. Rootwads, logs, and armor stone were delivered throughout the week.