Rootwad trees and logs were delivered to the site. The slide structure at the campground was completed and work began backfilling the structure and constructing the adjacent ELJs. The upper channel continued to be widened with material placed at the slide structure. Boulders were delivered to the site for helicopter placements and holes were drilled for anchorage. Top soils were spread at the middle reaches. Final sub-grading of the eastern portion of the looping trail was almost complete. A trail consultant, the planting subcontractor, and landscape architect visited the site.