Project Update – 9/30/17

The demolition of the dam began this week, where a series of notches were made at the top of the spill way, drawing down the surface of Mill Pond over 6 feet (Photos 1 & 2). The timber crib dam continued to be removed. One of two large woody structures were completed to fortify unstable slopes up stream of Mill Pond (Photos 3 & 4). Log jams were constructed to influence Sullivan Creek when it is put to the excavated starter channels (Photo 5).