Envirocon crews installed a ramp to the new bathroom at the campground, constructed a trail at the old boat ramp location to the creek edge, installed a short culvert at the elk creek trailhead, and performed weed spraying throughout the site. Subcontractors performed concrete work for the historic site ADA parking/sidewalk, Picnic shelter stairs and picnic shelter footings.
Project Update 7-14-2019
Project Update 7-7-2019
Project Update 6-30-2019
Envirocon crews completed finish grading around the project site and started the grading of the historic/campground site day use and ADA parking spots.
Project Update 6-23-2019